ALMONTY INDUSTRIES NEWS

Almonty Korea Tungsten, 19 March 2020 – Pilot plant starts full throttled continued operation producing concentrate.

We’re pleased to announce throughput is being achieved. Fine-tuning and calibration is now underway towards achieving the required WO3 grade and recovery targets.

  • Crushing unit capable of crushing 1 ton+ of ore per hour
  • Ball mill optimized for desired particle size and density
  • Ball mill optimized for desired particle size and density
  • Scheelite rougher – 2-stage flotation of scheelite with a scavenging cell
  • Scheelite cleaning unit – 3-stage cleaning for grade concentration
  • Scheelite cleaning unit – 3-stage cleaning for grade concentration

Lab equipment packed at Los Santos, ready for dispatch to Almonty Korea Tungsten